The Impacts of Wholesale Market Rules and Policies on Clean Energy Goals

A Primer for Local Governments

Appendix A. Barriers to and Opportunities for Solar in ISO-NE

Characteristics

The ISO-NE footprint covers six states: Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island, and Vermont (Figure A1). All six states participate in the Regional Greenhouse Gas Initiative, and Massachusetts sets additional emissions limits for electric generating units through the state’s Global Warming Solutions Act.

Figure A1 | ISO-NE’s Footprint

Source: Sustainable FERC Project n.d.

ISO-NE has a real-time average hourly load of 13.3 GW. The supply mix is dominated by natural gas (42 percent), followed by nuclear (22 percent) and imports (20 percent, which is primarily hydroelectric imports from Canada). In 2020, solar accounted for 2 percent of the supply mix. However, the amount of solar has been increasing rapidly since 2016 (ISO-NE 2021).

ISO-NE conducts forecasts of the total capacity of solar in the region, including behind-the-meter (BTM) resources that do not currently participate in its markets. These forecasts help to improve near-term operability and long-term planning. The most recent forecast shows that the total capacity will grow from just under 4,000 MW as of the end of 2020 to 10,000 MW by the end of 2030, a growth rate of 150 percent. Table A1 shows the growth of each category: solar resources that clear the Forward Capacity Market (FCM) auction and receive a capacity obligation; resources that do not have a capacity obligation and participate only in the energy market; and BTM resources (Black 2021).

Table A1 | Current and Projected Future Nameplate MW of Solar Capacity in ISO-NE

Year

FCM

Energy Only

Subtotal Wholesale

BTM

Total

Nameplate MW of solar capacity

2020

872.3

760.2

1,632.5

2,363.4

3,995.9

2030

1,347.6

3,320.2

4,667.8

5,365.1

10,032.9

Percentage of total

2020

21.8

19.0

40.9

59.1

100.0

2030

13.4

33.1

46.5

53.5

100.0

Source: Black 2021.

Transmission

Many of the broad transmission planning issues identified exist in ISO-NE. Although significant transmission investments have occurred throughout New England, increasing from US$869 million in 2008 to $2.4 billion in 2019, ISO-NE does not conduct transmission planning on a regular schedule to determine the total amount and type of transmission infrastructure needed to expand renewable resources and DERs and study the impacts of electrification (NESCOE 2020a).

The most recent regional transmission plan was issued in November 2021. Although FERC Order No. 1000 established that regional transmission processes must “provide for the consideration of transmission needs driven by public policy requirements,” ISO-NE has never done this (FERC 2011, 1; Marshall 2017). Although almost all states in New England have statutory requirements for greenhouse gas reductions, the New England States Committee on Electricity (NESCOE) stated to the ISO in 2020 that no federal or state public policies were driving transmission needs (Donovan et al. 2021b; NESCOE 2020b).

Transmission planning in ISO-NE uses a siloed approach that evaluates project benefits under a single category of “reliability,” “public policy,” or “economic” rather than a holistic multiple value approach. Although permitted by the ISO-NE tariff, to date, the region has never built a public policy or economic transmission project. Moreover, a number of stakeholders have expressed concern that there is not sufficient consideration of non-wires alternatives and their ability to reduce the need for new transmission (Donovan et al. 2021b).

There are a number of options for funding transmission upgrades within the ISO-NE tariff, including reliability transmission upgrades, the costs of which are shared among the states in proportion to their share of the regional load, and elective transmission upgrades, whereby project developers must pay 100 percent of grid upgrades. A number of stakeholders in ISO-NE have urged the ISO to undertake cost allocation reforms to determine methods that are agreed upon by the states, especially for elective transmission upgrades. Having developers pay the full cost of the upgrades causes many generators to then drop out of the queue (Donovan et al. 2021b). In 2017, ISO-NE adopted an approach that allows, under specific conditions, for two or more interconnection requests to be analyzed as a cluster so that interconnection costs can be allocated to a group of projects rather than sequentially to individual projects. Although the cluster approach may provide some benefits, it does not address the need to holistically plan the transmission system for the future resource mix (Pullaro 2021) or to ensure that the costs are allocated in line with the benefits received (Donovan et al. 2021b).

ISO-NE has pledged to conduct a long-term transmission study of the amount, type, and costs of transmission needed to deliver the study’s projected clean energy and DERs through 2050. This will not include recommendations for specific projects, however, and such projects can only move forward if one or more states elect to develop transmission to meet public policy requirements. ISO-NE has also pledged to incorporate language into its tariff for the continuation of such scenario-based transmission planning (NESCOE 2021).

Capacity Valuation

Clean energy advocates in New England have pointed out that a number of rules reduce the value of solar and other renewable resources for their buyers, for the following reasons (Krich 2021):

  • Wind and solar are qualified only based on their actual energy deliveries during times of higher system stress, but traditional resources are credited based on their maximum output capability as demonstrated during a brief seasonal audit and not based on actual delivery.
  • The “overlapping impact” test requires new resources to demonstrate that they are incrementally deliverable to the geographic area where the capacity will be used to qualify to submit an offer into the capacity market, but existing resources are running at their full capacity interconnection rights. Because renewable sources are newer to the system, their capacity is sometimes “blocked” by existing fossil-fueled generation.
  • Energy-only solar generators that do not participate in the FCM are not counted toward the installed capacity requirement, which is projected to apply to one-third of all solar energy installed in the region in 2030. As a result, these resources neither reduce the installed capacity requirement nor provide low-cost capacity supply, raising the capacity obligation for all LSEs and requiring those who contract with energy-only solar to pay twice to meet their capacity obligation.

ISO-NE has initiated an effort to “identify and implement methodologies that will more appropriately accredit resource contributions to resource adequacy,” and it is “contemplating” a filing at FERC at the end of 2022 (Chadalavada 2021, 5).

Regarding hybrid resources, ISO-NE reports that it does not have specific rules for colocated or hybrid resources, and they can participate in all markets. In 2020, the ISO reported that over 75 colocated facilities either qualified in 2019 or were expected to be qualified in 2020 to participate in the capacity auction, of which 32 requested qualification as single hybrid resources (Wolfson and Boucher 2020). The total capacity of all these resources equaled 220 MW of summer capacity (Wolfson and Boucher 2020), which is less than 1 percent of the total capacity of resources qualified for the capacity auctions held in 2020 and 2021 (Rost 2021).

Hybrid resources are currently not a significant portion of the interconnection queue for ISO-NE (ISO-NE n.d.a.). In 2021, they totaled just 3 percent of queue capacity, and all of these hybrid resources were solar-plus-storage (ISO-NE 2021).

Capacity Market/Minimum Offer Price Rule

ISO-NE has a mandatory capacity market (the FCM) that procures capacity for a 12-month period, 40 months in advance of when that capacity must be available. The 16th Forward Capacity Auction (FCA 16) was held in February 2022 and procured capacity for the June 2025–May 2026 period.

Under ISO-NE’s MOPR, any new resource offering capacity into the auction for the first time must submit an offer equal to or above an offer review trigger price (ORTP) established by ISO-NE. If the resource wishes to submit an offer below the ORTP, it must demonstrate to the Internal Market Monitor (IMM) that such an offer is justified by its costs and anticipated market-based revenues.

For FCAs 11–15, the IMM reviewed nearly 490 requests to offer below the ORTP, and it denied 341 of these new supply offers, which were required to offer into the auction at a higher price than requested by the resource developer. The IMM, however, does not report on these offers by resource type (ISO-NE 2021).

Although the amount of solar that has cleared the FCA has increased from 60 MW to 420 MW between FCA 10 (procuring capacity for the 2020–21 period) and FCA 15 (for the 2024–25 time frame), it is still just 1.2 percent of total resources clearing the auction (ISO-NE 2021). Moreover, only 18 MW of new solar cleared in the 2021 auction, which is 0.7 percent of new resources (Rost 2021).

ISO-NE attempted to accommodate renewable resources being developed pursuant to state policies by implementing a new rule: the Competitive Auctions with Sponsored Policy Resources (CASPR). Under CASPR, implemented in the 2019 FCA, resources that clear the FCA but then decide to retire can purchase capacity from state-sponsored renewable resources that did not clear the auction due to the application of the MOPR. The retiring resources would receive a “severance” payment equal to the difference between their capacity price and the amount paid to the state-sponsored resource. CASPR requires an existing resource exit to make room for a new renewable resource to enter.

CASPR, however, has proved to be ineffective; only one 54 MW portion of an offshore wind project cleared through its substitution auctions in three years. The substitution auctions were not even held in FCA 14 and FCA 15, despite nearly 300 MW and 228 MW, respectively, of state policy resources seeking to enter through those auctions because there were no retiring resources seeking to purchase their capacity (Turner et al. 2021b). A provision of CASPR that provided a means for solar to clear the auction in greater numbers was the Renewable Technology Resource (RTR) exemption from the MOPR. But ISO-NE eliminated the RTR after the most recent FCA, and only a limited amount of the exemption remained in FCA 15 (ISO-NE 2021).

ISO-NE has recently put in place a specific ORTP value for solar to replace the default ORTP of the starting price in the auction, which it did not have previously. Both ISO-NE and the New England Power Pool (NEPOOL) had submitted different proposed ORTPs for solar, and FERC approved ISO-NE’s higher threshold. ISO-NE had been working with stakeholders to develop tariff revisions to remove the MOPR and replace it with very narrow buyer-side market power provisions that would accommodate state and local government renewable procurement, but it recently decided that such changes would not be made until the 2025 auction. In exchange, the ISO will reinstate a 700 MW RTR for the next two capacity auctions.

Decision-Making and Stakeholder Processes

Along with the common concerns about the lengthy and complex stakeholder process, there are several concerns specific to the ISO-NE process, which is conducted by NEPOOL, a private advisory stakeholder body.

NEPOOL decision-making is the least transparent of all the RTOs, and its meetings are not open to the general public or the press (unless the member of the press becomes a member). Only NEPOOL members, NESCOE, and ISO-NE staff may attend. A member of the public may attend only as an invited guest, and although meeting materials are public, all conversations are confidential. ISO-NE board meetings are also closed to the public and press, and only members of the board and ISO-NE management may attend (Parent et al. 2021).

Along with large energy users, environmental groups and consumer advocates are included as NEPOOL members in the end-use sector. The sector’s vote in the NEPOOL Participants Committee is weighted by one-sixth, which dilutes the votes of these public interest entities (Donovan et al. 2021a). (All six sectors each have equal voting weight.) The Participants Committee is the senior committee that serves as the primary avenue for input to the ISO-NE board (Parent et al. 2021).

Although states are generally represented by the state commissions in the RTOs, there are two state entities that participate in ISO-NE stakeholder processes: NESCOE, which represents the interests of the New England governors, and the New England Conference of Public Utility Commissioners (NECPUC), representing the state commissions. NESCOE focuses primarily on resource adequacy and transmission planning. NECPUC addresses a range of wholesale market issues that are of interest to the state commissions and also participates in the board of director nominating process (Chen and Murnan 2019). Yet these entities have a limited voice in decisions, with the only formal role for the states being NESCOE’s ability to vote on the determination of the reserve margin (Donovan et al. 2021a). NESCOE is, however, allowed to make proposals in the NEPOOL technical committee meetings; propose alternative cost allocation provisions to those proposed by transmission owners, which must be included in the filing to FERC; and identify how some of the costs of public policy transmission projects are allocated (Parent et al. 2021).

Meetings of the ISO-NE Planning Advisory Committee, which provides input to the ISO on transmission planning, are open to the public, but no voting occurs in this committee (Parent et al. 2021). The committee will provide a forum for the discussion of ISO-NE’s 2050 transmission study.

In October 2020, NESCOE took steps outside of the formal stakeholder process to address shortcomings in the ISO rules and policies, with the release of a statement “for a clean, affordable, and reliable 21st century regional electric grid,” which identified needed reforms to wholesale electricity market design, transmission, and governance (NESCOE 2021). Following the release of this statement, the New England states held a series of forums that addressed wholesale market design, transmission planning, governance, and equity and environmental justice; these forums were followed by a June 2021 report from NESCOE providing its recommendations (NESCOE 2021). The forums established a foundation for future engagement by establishing the needed areas of reform.

Order No. 2222

With the growth of solar energy in New England, implementing Order No. 2222 is important for wholesale market participation of BTM and community solar as well as demand response and other responsive DERs, such as electric vehicles, which can balance the intermittency of that solar.

ISO-NE submitted its compliance filing with Order No. 2222 on February 2, 2022. Stakeholders supporting DERs had advocated for tariff changes that would allow all types of DERs to participate in the wholesale markets and reduce burdens to such participation (Dwyer 2021). Environmental groups, as well as a number of demand-response, energy efficiency, and renewable energy companies, abstained or objected to ISO-NE’s final proposal in the stakeholder process.

Table A2 | Relevant Issues in ISO-NE and Implications for Local Governments

Issue

Definition/Brief Explanation

Implications for Local Governments

ISO-NE Status

Transmission planning

Planning does not always sufficiently incorporate new renewable development, interregional transmission, and non-wires alternatives

Reduces access to renewable resources; creates inefficiencies and excess transmission costs

Initiated a long-term study of the amount, type, and costs of transmission needed to deliver projected clean energy and DERs through 2050

Interconnection and cost allocation

Many renewable projects drop out of the queue due to high interconnection costs

Can delay and increase cost of renewable procurement

Allows for a cluster approach to assigning interconnection costs, which provides some improvements

Capacity accreditation

Current rules reduce the value of solar and other renewable resources

Unbalanced valuation of renewables can create additional procurement costs

Planning to develop improved valuation methodologies; thus far, has just held information sessions

Capacity markets/MOPR

The Forward Capacity Market includes a MOPR applicable to renewable energy

Creates uncertainty, delays, and additional costs for renewable procurement

Changed course in February 2022 by delaying its proposed end date for use of a MOPR from the 2023 capacity auction to the 2024 capacity auction

Hybrid resource market participation

No rules specifically target hybrid resources, and they are allowed to participate in the markets

Improved market rules will ease the development of hybrid resources and improve procurement

Limited amount of hybrids expected to come online in the near future

DER wholesale market participation

Developing rules to allow for greater DER participation in the market within the stakeholder process

DER participation in the markets can allow more storage and demand-side resources to balance renewables, increasing the value of the contracts, and can provide additional revenue to local government-owned solar and storage resources

Proposed rule changes to include DERs in the markets filed at FERC on February 2, 2022

Stakeholder processes

Highly opaque and participation is greatly restricted

Both local governments and supporters of renewable energy can face difficulties in ensuring that barriers are reduced for renewable energy procurement

One of the workshops held last year as part of the state-initiated New England Energy Vision initiative addressed governance and the need for reforms

Notes: DER = distributed energy resource; FERC = Federal Energy Regulatory Commission; ISO-NE = Independent System Operator New England; MOPR = Minimum Offer Price Rule.

Start reading